HomeBlogHow Draw Schedules Work on Ground-Up Construction Loans (And What Happens When Your Builder Blows One)
Back to all articles
Uncategorized

How Draw Schedules Work on Ground-Up Construction Loans (And What Happens When Your Builder Blows One)

RoadToFirstMillion
RoadToFirstMillion
August 13, 2026
7 min read

How Draw Schedules Work on Ground-Up Construction Loans (And What Happens When Your Builder Blows One)

If you’ve ever tried to get a ground-up construction loan from a bank, you already know the routine: six months of paperwork, a committee that moves like it’s 1987, and a loan officer who doesn’t understand what an ARV is. But even with private lenders and hard money, there’s one piece of the process that trips up experienced investors every single time: the draw schedule.

Get the draw schedule right and your project runs like a machine. Get it wrong and you’re standing on a half-framed shell in August, out of cash, with a subcontractor threatening to file a mechanics lien. Neither of us wants that.

This is the part nobody explains clearly upfront. So let’s fix that. Apply now at slatefinancial.io/apply and let’s talk about what your draw schedule actually looks like before you close.

What Is a Draw Schedule, Exactly?

A draw schedule is the payment plan between you (the borrower) and your lender during construction. Instead of handing you a lump sum on day one — which no lender would do — funds are released in stages as verified milestones are completed.

Think of it as the lender saying: “We’ll believe you completed the framing when someone physically confirms the framing is done.” That someone is the draw inspector, and those inspections are what trigger each payment release.

Typical draws are broken into 4 to 7 stages depending on the project and the lender. A standard ground-up residential project might look like this:

  • Draw 1 (Foundation): Footings poured, foundation complete, rough plumbing in slab. Usually 10-15% of the construction budget.
  • Draw 2 (Framing): Walls up, roof decked, exterior sheathed. Another 20-25%.
  • Draw 3 (Rough-Ins): HVAC, electrical, plumbing roughed in and inspected. 15-20%.
  • Draw 4 (Drywall and Insulation): Board hung, taped, insulation installed. 10-15%.
  • Draw 5 (Finishes): Flooring, cabinets, fixtures, paint, trim. 20-25%.
  • Draw 6 (Certificate of Occupancy / Final): CO issued, punch list done. Final 10% held until project is fully complete.

The percentages above are illustrative — your actual schedule will be negotiated with your lender based on your scope of work and budget. This is one reason it pays to work with a lender who understands construction, not just a bank that issues a term sheet and disappears.

How the Draw Request Process Actually Works

Here’s the part builders and investors get confused about: you do not automatically receive draw funds when a milestone is complete. You have to request the draw. The sequence is:

  1. Complete the milestone. Your GC or subs finish the scope of work for that draw stage.
  2. Submit a draw request. You (or your GC) submit a formal request to the lender, typically with invoices, lien waivers from contractors, and photos.
  3. Inspector visits the site. A third-party draw control inspector confirms the work is complete and matches the request. This usually takes 2-5 business days from scheduling.
  4. Lender approves and funds. Once the inspection report is in, the lender wires the draw. Expect 3-7 business days total from request to cash in your account.

That 3-7 day window is where projects run into trouble. If your contractor expects payment the moment they finish framing, and your lender takes 5 days to fund the draw, you need a cash cushion or you need a very patient GC. Plan for this gap from day one.

What Happens When a Draw Gets Rejected

Draw inspectors are not rubber stamps. They flag incomplete work, work that doesn’t match the approved plans, or items billed that weren’t done. Common rejection reasons:

  • Overbilling: Your GC bills for 100% of framing but the inspector finds it’s 80% complete.
  • Code violations: Work was done but failed inspection from the municipality — the draw inspector won’t sign off on something that hasn’t passed local inspection.
  • Missing lien waivers: Subcontractors who haven’t signed conditional lien waivers before the draw create title risk. Most lenders won’t release funds without them.
  • Scope creep: Work outside the approved budget was completed and your GC expects reimbursement. Changes need lender approval in advance.

A partial draw approval is common — you might request $60,000 and receive $48,000 because the inspector found the framing 80% complete. The remaining $12,000 releases on the next draw when framing is confirmed done.

This is why your GC relationship matters as much as your lender relationship. A GC who games the draw process, or who runs behind schedule, can put your entire project timeline in jeopardy — and your interest clock doesn’t stop for any of it.

The Interest Reserve: How You Pay During Construction

Most ground-up construction loans are interest-only during the build phase. But if you don’t have cash flow coming in during construction, how do you make those payments?

The answer is an interest reserve — a portion of the loan budget set aside specifically to cover interest payments during construction. Here’s how it works:

Let’s say you’re building a $400,000 spec home. Your all-in loan (land + construction) is $350,000 at 11% interest. Monthly interest on the full amount would be roughly $3,200/month. But in month one, you’ve only drawn $50,000 for site work and foundation — so you’re only paying interest on that $50,000 (~$460/month).

Your lender builds a 12-month interest reserve into the loan (estimated at $24,000 for a 12-month build). That reserve is held in escrow and used to make your monthly payments automatically. You don’t write a check — the lender pulls from the reserve account each month.

This matters when you’re underwriting the deal. Your total project cost is land + construction + interest reserve + closing costs + holding costs + your profit margin. The interest reserve is not free money — it’s part of your loan and it comes out of your proceeds at sale. Underwrite it correctly from the start.

Ready to run your numbers? Start your application at slatefinancial.io/apply and let us structure the right loan for your ground-up project. Funding subject to lender approval.

The Construction-to-Perm Option (When It Makes Sense)

If you’re building a property you intend to keep as a long-term rental rather than sell, a construction-to-perm loan rolls your short-term construction financing directly into a permanent loan at project completion — no second closing, no second set of closing costs.

You close once. During construction, you’re in the draw phase. When the CO is issued, the loan converts automatically to a term loan (typically a DSCR loan structure for investors). This saves you 1-2% in closing costs on the takeout and eliminates the refinance risk — the risk that rates or your financial picture change between the time you break ground and the time you need to refinance.

The tradeoff: construction-to-perm loans are more complex to underwrite upfront because the lender is committing to both the construction phase and the permanent phase. They need to be comfortable with the completed value, your projected rents, and your DSCR at stabilization. More documentation, but one closing.

When Builders Blow the Draw Schedule (And What You Can Do)

Let’s talk about the scenario that keeps investors up at night: you’re four months into a six-month project, your GC is running two months behind, and your interest reserve is running thin. What are your options?

Option 1: Loan extension. Most private construction lenders offer extensions for 1-3 months at a fee (typically 0.5-1% of the loan balance). If your delay has a legitimate cause (permit delays, supply chain, weather), your lender would usually rather extend than foreclose. Communicate proactively — lenders hate surprises more than delays.

Option 2: Construction bridge loan. If your original lender won’t extend and you’re close to completion, a construction bridge loan can buy you the 60-90 days you need to finish and sell. Short-term, higher-rate, but it keeps the project alive.

Option 3: Working capital injection. If your GC ran over budget and the draw schedule doesn’t cover it, a short-term business line or working capital advance can fund the gap. This is where MCA products sometimes serve a legitimate purpose — bridging a gap in a construction timeline when the exit (sale proceeds) is certain. That said, stacking short-term debt on a construction project needs careful analysis of the total cost against your projected profit. Do the math before you sign.

If you’re in a bind on a project, reach out now. We work through these situations regularly. Apply at slatefinancial.io/apply and tell us exactly where the project stands — we’ll tell you what’s available.

How to Set Up Your Draw Schedule for Success

A few things that experienced builders do from day one that most first-timers learn the hard way:

  • Get your GC to sign off on the draw schedule before you close. If your GC expects money differently than your lender releases it, you have a conflict before you break ground. Align these upfront.
  • Build in a 10% contingency. Construction never goes exactly to plan. A 10% contingency reserve (held by the lender, released on documented change orders) is standard on any professionally structured loan.
  • Collect lien waivers before paying subs. Every sub who touches your project should sign a conditional lien waiver at each draw. This protects your title and your lender.
  • Schedule inspections early. Draw inspectors have backlogs. Once you know a milestone is 1-2 weeks from completion, request the inspection early so it’s scheduled and ready the day the work is done.
  • Document everything with photos. Time-stamped photos of each construction phase are your best defense against a disputed draw. Your GC should be doing this automatically. If they’re not, make it a contract requirement.

Ready to Fund Your Next Ground-Up Project?

Whether you’re building your first spec home or your twentieth, the mechanics of construction financing are the same: it’s all about how well the draw schedule is structured and how prepared you are to manage it.

At Slate Financial, we work with ground-up builders across Florida, Texas, Georgia, South Carolina, and beyond. We close construction loans in 3-4 weeks, not 6 months. Our lenders understand draw schedules, understand construction timelines, and understand that projects sometimes hit snags — what matters is how you manage through them.

Ready to fund your next deal? Apply in 2 minutes at slatefinancial.io/apply and tell us about your project. All funding subject to lender approval and underwriting review.

Need Business Funding?

Slate Financial matches you with the best funding options. Apply in minutes.

Apply Now - Free

Tags

Uncategorized
David R. Bizousky

RoadToFirstMillion

Founder & CEO, Slate Financial

David R. Bizousky is a financial services entrepreneur and the founder of Slate Financial, an alternative lending platform that connects business owners and real estate investors with the right lenders across all 50 states, powered by AI-driven underwriting.

Get the Funding Your Business Deserves

Get matched to the right lender in seconds. Apply in minutes.

Apply Now — It's Free
How Draw Schedules Work on Ground-Up Construction Loans (And What Happens When Your Builder Blows One) | Slate Financial Blog